On October 30, 2007, Canadian National Railway
(CN) filed an application with the Surface Transportation Board to acquire the
EJ&E West Company. This website contains information regarding the proposed
Canadian National Railway acquisition.
CN is one of Canada's two major
railroads. It extends
from Halifax, Nova Scotia, to Vancouver and Prince Rupert,
British Columbia. EJ&E currently operates over 198 miles of track in
northeastern Illinois and northwestern Indiana, consisting primarily of an arc
around Chicago, Illinois. This arc extends from Waukegan, Illinois, southward to
Joliet, Illinois, then eastward to Gary, Indiana, and then northwest to South
Chicago, Illinois, along Lake Michigan, as shown in the image. EJ&E provides
rail service to approximately 100 customers, including steel mills, coal
utilities, plastics and chemical producers, steel processors, distribution
centers, and scrap processors. CN's proposed acquisition of EJ&E would shift
rail traffic currently moving over CN's rail lines in Chicago to EJ&E rail
lines. Approximately 15 to 27 more trains per day would operate on various
segments of the EJ&E rail lines.
Click here and you can view what crossings will
be impacted the most. The complete grade crossing analysis can be downloaded by
clicking here.
For more information on the
Surface Transportation Board, please
click here. This
project fact sheet
provides a quick overview of the proposed acquisition and how to submit
comments.
Timeline and Review Process
The National Environmental Policy Act process assists the Surface Transportation
Board and the public in identifying and assessing the potential environmental
consequences of a proposed action before a decision is made. We have provided
you with important dates and brief outline of the additional steps in the
process used by the Surface Transportation Board. The entire process is outlined
in detail
here.
October 30, 2007
– Canadian National submitted their application to the Surface Transportation
Board to acquire a portion of the EJ&E Railway.
November 26, 2007
–
the Surface
Transportation Board issued its initial decision.
The Board determined the transaction to be "minor" but, also found that an
Environmental Impact Statement is warranted.
December 11, 2007
–
Mundelein filed a Notice of Intent to participate in the process with the
Surface Transportation Board.
December 21, 2007
–
A
Notice of Intent to prepare an Environmental Impact Statement was published.
Draft Scope of Study
– A draft Scope of Study is being developed for the Environmental Impact
Statement. The draft Scope of Study tries to incorporate the environmental
issues and concerns raised in the comment letters received already as well as
any potential concerns with regard to any aspect of the review process. Public
comments on the draft Scope of Study are requested.
January 8-22, 2008
– Seven public open house scoping meetings were held within the proposed study
area to gather information on potential project issues and concerns. Over 2,000
interested citizens attended the meetings. Members of the public can also submit
written comments at this stage of the process as well as electronic comments by
visiting the Surface Transportation Board’s website. Contract information is
provided below. Public comments on the draft Scope of Study are due February 15,
2008.
January 30, 2008
–
The
Village of Mundelein submitted their official comments on the Scope of Study.
April 25, 2008 -
Final Scope of Study prepared by Surface Transportation Board.
June 24, 2008 -
The Village of Mundelein
submitted additional comments to the Surface Transportation Board
concerning the final scope of the EIS.
July 25, 2008 - Draft EIS prepared by Surface Transportation
Board
August 19, 2008 -
The Village of
Mundelein submitted their preliminary comments on draft EIS.
August 26, 2008 - STB
Public Meeting on Draft Environmental Impact Statement
September 3, 2008 - Response from STB regarding the 60/83
crossing
September 8, 2008 - Surface Transportation Board Decision
-
STB Decision
regarding CN's Petition to Modify the Procedural
Schedule to Provide a Prompt Final Decision on the Merits Under 49 USC §
11324(d)(1) Subject to a Condition Preserving the Environmental Status Quo
Pending Environmental Review (CN-49)
September 26, 2008 -
Village of
Mundelein comments on Draft Environmental Impact Statement
September 29, 2008 -
ICC Comments
to Draft Environmental Impact Statement
December 5, 2008 -
Final Environmental Impact Statement
December 2008
- Village of Mundelein Signs Agreement with Canadian National.
You can view comments from other groups here. Additional comments will be posted as they are received.
ACQUISITION PROCESS
Final Scope of Study
– After the close of the comment period on the draft Scope of Study, all
comments received will be reviewed and then a final Scope of Study for the
Environmental Impact Statement will be issued.
Draft Environmental Impact Statement
– A Draft Environmental Impact Statement for the project will be prepared to
address those environmental issues and concerns identified during the scoping
process.
Public Comment
– Upon completion of the Draft Environmental Impact Statement, the document will
be made available for public and agency review and comment for 45 days.
Final Environmental Impact Statement
– A Final Environmental Impact Statement will be prepared that will address the
comments from the public and agencies.
Decision
- The Surface Transportation Board will review the Final Environmental Impact
Statement and then issue a decision on the proposed project.
More dates and information on
the acquisition will be added to the website as it becomes available. If you
would like more information on the acquisition please visit any of the websites
provided below. The Village of Mundelein would like to encourage you to become
involved in the process and submit your comments to the Surface Transportation
Board.
Contact Information
Comments
on the draft Scope of Study can be submitted in several ways:
-
Written Comments
-
Recorded Comments
-
Electronic Comments
Please note, submitting a
comment will also add your name to the mailing list for notice of the
distribution of the final Scope of Study, the Draft EIS, and the Final EIS. This
mailing list will also be used to distribute future meeting information as well
as any other important information regarding the project. You can be added to
the mailing list without submitting a comment by using the same contact
information listed below.
Please refer to STB Finance
Docket No. 35087 in all correspondence addressed to the Surface Transportation
Board.
Written Comments
The Surface
Transportation Board encourages broad participation in the process. Written
comments regarding the draft Scope of Study can be sent to:
Surface Transportation Board
395 E Street, SW
Washington, DC 20423
Attention: Phillis
Johnson-Ball
Environmental Filing
STB Finance Docket No. 35087
Recorded Comments
Comments
can be provided to a member of the project team or court recorder at the public
open house scoping meetings or by calling the project information line:
1-800-347-0689.
Electronic Comments
Electronic comments can be submitted by visiting the Surface Transportation
Board's website, www.stb.dot.gov, under the heading "E-Filing."
Links
EJ&J Construction update -
http://ejeupdates.cn.ca/
Surface Transportation
Board's environmental review –
www.stbfinancedocket35087.com
Surface Transportation Board
- www.stb.dot.gov
Canadian National Railway
Company- www.cn.ca
Elgin, Joliet and Eastern
Railway Company - www.tstarinc.com/eje/
Barrington Communities
Against CN Rail Acquisition -
www.fightrailcongestion.com/ |